Shipping
MAN B&W main engine installation on a 183 m tanker
Installation of a MAN B&W 6S50MC-C main engine (215 tonnes), intermediate shaft and intermediate shaft bearing, tail shaft and tail shaft bearing, on a 183 m tanker owned by a Greek shipping company.
The project included in-situ grinding on the base (stern tube boss) of the tail shaft’s bearings, supervision of the in-situ grinding of the tail shaft for acceptable straightness, and supervision of the propeller cone fitting in the tail shaft.
- 215 t
- Main engine weight
- 183 m
- Tanker length
Related services
10 Laser Alignment Inspection & Alignment Services Alignment inspections and alignment with state-of-the-art laser systems, 1.0 μm accuracy. 11 Straightness Inspection Direct laser straightness measurement — crankshafts, bearing pockets, rudder and hydro-turbine shafts. 13 In Situ Grinding Operations On-site grinding operations — engines, generators, bearings — without transport to a workshop.